  • Successful completion of Renovation and Modernization of 4x50 MW Kopili Hydro Power Station. The last unit i.e. Unit-I was declared for Commercial Operation on 03.06.2024.
  • Investment approval for Heo HEP (240 MW) and Tato-I HEP (186 MW) in Arunachal Pradesh have been accorded by CCEA, Govt. of India on 11.12.2024.
  • PIB meeting for Tato-II (700 MW) held on 15.05.2025.
  • Contract for Package- I (Civil works) and Package-II (HM works) has been awarded for Tato-I HEP (186 MW).
  • EPC Contract (Civil & HM Package) of Heo HEP (240 MW) has been awarded.
  • MOU signed with BRO for deposited work of internal road (30 KM approx.) for Tato-II HEP (700 MW).
  • Notification of Award (NoA) for 300 MW Solar PV project in Bikaner, Rajasthan issued.
  • Foundation stone of 300 MW Solar PV project in Bikaner, Rajasthan laid by the Hon’ble Prime Minister of India on 22.05.2025.

 

Performance at a Glance

Particulars2024-252023-242022-232021-222020-21
Authorized Capital (Rs in Crs.) 5000.00 5000.00 5000.00 5000.00 5000.00
Paid-up Capital (Includes Share Application Money Pending Allotment) (Rs. in Crs.) 3609.81 3609.81 3609.81 3609.81 3609.81
Installed Capacity (MW) 2057 2057 2057 2057 2057
Generation (MU) 8020.00 8001.00 8492.00 8120.29 6869.86
Sales (Rs. in Crs.) 4297.79 4239.57 4557.27 3206.84 2288.09
Profit Before Tax (Including Rate Regulatory Income) (Rs. in Crs.) 860.19 595.24 748.01 433.45 90.91
Profit After Tax 584.69 548.12 396.90 212.29 47.90
Total Income (Rs. in Crs.) 4341.87 4264.22 4570.64 3301.97 2554.44
Dividend (Rs. in Crs.) 200.00 300.00 300.00 90.00 15.00
Man/MW Ratio 0.77 0.82 0.86 0.93 0.99