- MOA was signed with State Govt. on 20.04.2012.
- Draft DPR for an installed capacity of 75 MW was submitted to CEA for scrutiny by CEA.
- As observed by CEA, the DPR is under revision for an installed capacity of 85 MW.
- Comprehensive environmental studies are in process.
Testing future project
  
 English
Name of The Project: 
Mawphu HEP Stage-II (85 MW)
Commissioning Schedule: 
5 years
 
										 
									