Hydro Projects

Last Updated : 05/06/2020

Sl. No Project Name Location / State Installed Capacity (MW) Total Capacity (MW) Status
1 KOPILI HYDRO ELECTRIC PLANT Umrongso, District-Dima Hasao, ASSAM 200 + 50 + 25 275 Completed
2 RANGANADI HYDRO ELECTRIC PLANT Yazali, District-Lower Subansiri, Arunachal Pradesh 3 X 135 405 Completed
3 PARE HYDRO ELECTRIC PLANT Papum Pare District, Arunachal Pradesh 2 x 55 110 Completed
4 DOYANG HYDRO ELECTRIC PLANT District - Wokha, Nagaland 3 X 25 75 Completed
5 TUIRIAL HYDRO ELECTRIC PLANT Kolasib District , Mizoram 2 x 30 60 Completed
6 KAMENG HYDRO ELECTRIC PLANT (Commissioned) West Kameng District of the State of Arunachal Pradesh. 2 x 150 300 Completed
SUB TOTAL: 1225
7 KAMENG HYDRO ELECTRIC PLANT (Ongoing) West Kameng District of the State of Arunachal Pradesh. 2 x 150 300 Ongoing
SUB TOTAL: 300
GRAND TOTAL : 1525