Projects To Be Taken Up

Last Updated : 02/05/2019

Future projects of NEEPCO in ownership basis are as follows:

HYDRO

SL. NO NAME OF THE PROJECT STATE STATUS COMMISSIONING SCHEDULE 
(TENT. FROM INVESTMENT APPROVAL)
1 Wah Umiam HEP Stage-III (85 MW) Meghalaya
  • DPR submitted to CEA and TEC is expected shortly. Pre-investment approval obtained from MoP.
  • Comprehensive environmental studies completed. EAC recommended for grant of Environmental Clearance subject to Stage-I Forest Clearance (FC-I).
  • FC-I taken up with State Forest Department.
  • Concerned departments of the State Govt. have been pursued for land acquisition, survey and construction of approach roads as a part of the Pre-construction activities.
5 years
2

Wah Umiam Stage-I HEP (50 MW)

Meghalaya
  • Govt. of Meghalaya allotted the projects to NEEPCO on 12.03.2019.
  • Signing of MoA is in process.
  • Preparation of PFR has been taken up.
5 years
3

Wah Umiam Stage-II HEP (100 MW)

 

RENEWABLE

SL. NO NAME OF THE PROJECT STATE STATUS COMMISSIONING SCHEDULE 
(TENT. FROM INVESTMENT APPROVAL)
1 Solar PV Project at Dhenkanal (200 MW) Odisha
  • The project is under various stages of central / state clearances
15 months from Date of signing of PPA