Future projects of NEEPCO in ownership basis are as follows:
HYDRO
SL. NO |
NAME OF THE PROJECT |
STATE |
STATUS |
COMMISSIONING SCHEDULE
(TENT. FROM INVESTMENT APPROVAL) |
---|
1 |
Tato-II HEP (700 MW) |
Arunachal Pradesh |
- MoA signed with Govt. of Arunachal Pradesh on 12.08.2023
- Investment approval is in progress.
|
72 Months |
2 |
Naying HEP (1000 MW) |
Arunachal Pradesh |
- MoA signed with Govt. of Arunachal Pradesh on 12.08.2023
- Updated project cost is under CEA vetting.
|
72 Months |
3 |
Hirong HEP (500 MW) |
Arunachal Pradesh |
- MoA signed with Govt. of Arunachal Pradesh on 12.08.2023
- DPR is under revision considering e-flow as per Basin Study Report.
|
72 Months |
4 |
Kurung HEP (330 MW)
|
Arunachal Pradesh |
- Preparation of PFR / DPR is in progress.
- Comprehensive Environmental Studies are in progress.
|
60 Months |
5 |
Nafra HEP (120 MW) |
Arunachal Pradesh |
- Project viability is yet to be re-established.
|
|
6 |
New Melling HEP (90 MW) |
Arunachal Pradesh |
- Project viability is yet to be established.
|
|
7 |
Wah Umiam St-III HEP (85 MW) |
Meghalaya |
- MoA was signed between the Govt. of Meghalaya and NEEPCO on 20th April, 2012.
- Techno-Economic Appraisal from CEA was received on 26th July, 2021.
- Environmental Clearance recommended by MoEF&CC, subject to Stage-I Forest Clearance (FC-I).
- FC-I is under process with Forest Department, Govt. of Meghalaya.
- Land acquisition survey is partly completed.
|
55 Months |
8 |
Wah Umiam Stage-I HEP (50 MW) |
Meghalaya |
- MoA signed with Govt. Of Meghalaya on 25.10.2022.
- PFR prepared. Project cost and tariff are on higher side.
|
|
9 |
Wah Umiam Stage-II HEP (100 MW) |
Meghalaya |
- MoA signed with Govt. of Meghalaya on 25.10.2022.
- PFR prepared. Project cost and tariff are on higher side.
- Integrated development with one PSP is under consideration.
|
|
Pumped Storage Project: |
|
|
|
|
1 |
Kopili PSP (320 MW) |
Assam |
- MoU signed with Govt. of Assam on 26.02.2025.
- PFR prepared. DPR is under preparation.
|
|
Floating Solar Project: |
|
|
|
|
1 |
Kopili FSP (40 MW) |
Assam |
- DPR prepared. Process for tendering is going on.
|
12 Months |