Projects To Be Taken Up

Last Updated : 21/05/2025

Future projects of NEEPCO in ownership basis are as follows:

HYDRO

SL. NO NAME OF THE PROJECT STATE STATUS COMMISSIONING SCHEDULE 
(TENT. FROM INVESTMENT APPROVAL)
1 Tato-II HEP (700 MW) Arunachal Pradesh
  • MoA signed with Govt. of Arunachal Pradesh on 12.08.2023
  • Investment approval is in progress.
72 Months
2 Naying HEP (1000 MW) Arunachal Pradesh
  • MoA signed with Govt. of Arunachal Pradesh on 12.08.2023
  • Updated project cost is under CEA vetting.
72 Months
3 Hirong HEP (500 MW) Arunachal Pradesh
  • MoA signed with Govt. of Arunachal Pradesh on 12.08.2023
  • DPR is under revision considering e-flow as per Basin Study Report.
72 Months
4

Kurung HEP (330 MW) 

Arunachal Pradesh
  • Preparation of PFR / DPR is in progress.
  • Comprehensive Environmental Studies are in progress.
60 Months
5 Nafra HEP (120 MW) Arunachal Pradesh
  • Project viability is yet to be re-established.
 
6 New Melling HEP (90 MW) Arunachal Pradesh
  • Project viability is yet to be established.
 
7 Wah Umiam St-III HEP (85 MW) Meghalaya
  • MoA was signed between the Govt. of Meghalaya and NEEPCO on 20th April, 2012.
  • Techno-Economic Appraisal from CEA was received on 26th July, 2021.
  • Environmental Clearance recommended by MoEF&CC, subject to Stage-I Forest Clearance  (FC-I).
  • FC-I is under process with Forest Department, Govt. of Meghalaya.
  • Land acquisition survey is partly completed.
55 Months
8 Wah Umiam Stage-I HEP (50 MW) Meghalaya
  • MoA signed with Govt. Of Meghalaya on 25.10.2022.
  • PFR prepared. Project cost and tariff are on higher side.
 
9 Wah Umiam Stage-II HEP (100 MW) Meghalaya
  • MoA signed with Govt. of Meghalaya on 25.10.2022.
  • PFR prepared. Project cost and tariff are on higher side.
  • Integrated development with one PSP is under consideration.
 
Pumped Storage Project:        
1 Kopili PSP (320 MW) Assam
  • MoU signed with Govt. of Assam on 26.02.2025.
  • PFR prepared. DPR is under preparation.
 
Floating Solar Project:        
1 Kopili FSP (40 MW) Assam
  • DPR prepared. Process for tendering is going on.
12 Months